EOT crane final acceptance and document handover

EOT Crane Document Handover Register

Quick Answer

Before final EOT crane acceptance, collect approved drawings, electrical schematics, BOM and makes list, datasheets, FAT report, load test certificate, SAT report, snag closure sheet, O&M manual, lubrication and maintenance schedules, spares list, warranty certificate, service contacts, and training records.

Missing documents create long-term maintenance problems. The crane may run today, but without drawings, manuals, certificates, and spares data, the buyer becomes dependent on memory and vendor goodwill.

Documents to Track

DocumentRequired StageWhy It Matters
Approved GA drawingBefore manufacturingLocks geometry and approval basis.
Electrical schematic and panel drawingBefore dispatchNeeded for troubleshooting.
BOM and makes final listBefore dispatchConfirms supplied components.
FAT and SAT reportsDispatch and final acceptanceAcceptance evidence.
Load test certificateBefore final acceptanceProof of tested capacity.
O&M manual and schedulesBefore final acceptanceSupports safe operation and maintenance.
Warranty and service contactsBefore final acceptanceControls support after handover.

Buyer Rule

  • Do not release final payment only because the crane is moving.
  • Use a document register with received/approved status.
  • Keep snag closure and final documentation together.
  • Ask for editable and PDF copies where practical.